Report of the Auditor General—November 2020
 

We assessed the two outstanding recommendations from March 2015 for the Dam Safety Program. We found both of these recommendations have been implemented:

  • Develop a plan to regulate dams and report on the results of regulatory activities
  • Improve regulatory activities by:
    • maintaining a reliable registry of dams
    • obtaining sufficient information to assess the risk and consequences of dam failure
    • retaining evidence of regulatory activities performed
    • following up to ensure that owners correct deficiencies or manage them until they are corrected